The First Narayever Congregation: Long-term strategic options

May, 2010

Background and context

The Changing Profile of Toronto's Downtown Jewish Community

Membership

Most Narayever members live within 9 km of the shul

map of membership

Needs Assessment

The subcommittee asked each Board member to express their opinions about how their needs were being met or not. Their comments in some places have undergone minor editing.

Adult Education

Bar/Bat Mitzvah

Celebrations

Building

Kiddush

Administration

The Rabbi's point of view

Online Survey: The needs of shul members

We conducted an online questionnaire of shul members. The responses were self-selecting (voluntary). We have so far obtained ~90 responses (as of 3/2/2010).

The respondents' demographics are as follows:

Members are generally satisfied with space; space for youth programming, celebrations and Kiddush present the greatest challenges.

results graph: satisfaction

People have had to restrict invitees to an event primarily due to space constraints in the sanctuary and the social hall.

results graph: restrictions

What are our options?

Option Description Cost Advantages Disadvantages
A Existing Site Renovate building; Options for rear addition, or second floor TBD
  • Maintain Location
  • No acquisition or land costso
  • Renovation costso
  • Zoning in placeo
  • Accessibility addressed
  • New interim location required
B Existing Site Tear down building and build new TBD
  • A new "ideal" building
  • Zoning issues and heritage may preclude option
C Purchase adjacent building to south Purchase building and build new building adjoined to existing shul TBD
  • Maintain existing location and gain new structure.
  • Acquisition includes land and renovation costs o
  • Zoning issueo
  • Site must be available
D Alternate place of worship Find an available shul or church for purchase and renovation TBD
  • Acquisition includes land & renovation costso
  • Few available sites in downtown o
  • Extended timeframe
E Alternate site Find a building or site TBD
  • Acquisition includes land & renovation costso
  • Zoning issues o
  • Extended timeframe
F Do nothing Keep building and restrict membership Nil
  • No financial cost
  • Space and program restrictionso
  • No Accessibility